Atrasos

O aplicativo Manufacturing (Manufatura) do Odoo exibe atrasos nas ordens de manufatura através do filtro Produções Atrasadas. Se a data final da MO (manufacturing order) exceder seu prazo, o prazo é destacado em vermelho para chamar atenção ao atraso.

The delayed production filter in Odoo.

Cálculo do prazo

O prazo da MO (manufacturing order) depende de como a MO (manufacturing order) foi criada e é calculado da seguinte forma:

  • Make To Order: the MO (manufacturing order) deadline is the Sales Order Delivery Date.

  • Replenishment: the MO (manufacturing order) deadline is today + Manufacturing Lead Time.

  • Manually created MO: the deadline field remains empty.

A data final é calculada como:

End date = Scheduled start date + Total duration of all operations

Filtros

Vários filtros adicionais estão disponíveis para ajudar a rastrear atrasos:

  • Delayed Productions: the MO (manufacturing order)'s scheduled start date is later than the deadline.

  • Late: the MO (manufacturing order)'s scheduled end date exceeds the deadline, highlighted in red.

  • Late Availability: one or more required components are not available before the deadline. For example, a confirmed purchase order or manufacturing order for components is scheduled to end after the MO (manufacturing order) deadline.

  • Components Available: all components are available to begin production.

Caso de uso

Considere uma MO (manufacturing order) com prazo de 17 de setembro:

  • If production on the MO (manufacturing order) starts after September 17th, it appears in the Delayed Productions filter.

  • If required components are scheduled to arrive after September 17th, the MO (manufacturing order) appears in the Late Availability filter.

  • If the MO (manufacturing order) has a scheduled end date after September 17th, it appears in the Late filter.

An MO with the deadline emphasized.

Ao combinar esses indicadores, os planejadores podem identificar rapidamente onde a produção corre o risco de perder os compromissos de entrega.